> I decided that the translators should start their work on next monay. They
> will have one month to finish their work.
> The handbook has to be finished until Monday, because it should also be
> trsnalted.
>
> The final release of 1.0 is scheduled for the 27th of May. Packages have to
> be created between the 34th and 27th of May.
> Is this release plan OK for you?

This works for me unless something breaks betwwen now and then but it seems 
to be running well. If I have the time I'll make sure redhat 7.1 packages get 
up there as well. I'll let you know before hand if the compiler for redhat 
7.1 is broke. If this is the case then red hat will take longer. 

Also Caldera 3.1 is going beta and I'll try to get up packages for it also.

>